Watch VideoStubbe’s Precast Plant #3

Project Value:

$42,000,000

Owner:

Stubbe's Commercial Precast Inc.

Consultant:

HGS Limited

Challenge:

  • Manage pre-construction and construction of a 208,000 SF  fully automated precast fabrication facility
  • Install state-of-the-art robotic carousel (the only one of its kind in Canada)

Objective:

Assist with value engineering and to implement construction methods into the design that would allow for the quickest possible procurement for the intended design.

Ensure that the complex building systems would work with the massive production building, and the specialized equipment that was contained within.

As a result, mechanical and electrical building equipment was ordered before construction began.

[More]

Watch VideoVivere New Head Office and Distribution Centre

Project Value:

$3,100,000

Owner:

Vivere Ltd.

Consultant:

Tacoma Engineers Inc.

Challenge:

  • Construct a new 6,500 SF office and 21,000 SF pre-engineered warehouse for Vivere's head office located in Guelph, Ontario.

Execution:
The work included concrete forming, rebar, concrete supply, masonry, structural steel, miscellaneous metals, EIFS, insulated roof and wall panels, hollow metal doors and frames, glass and glazing, drywall, flooring, painting, mechanical, electrical, site work and landscaping.

CNG Fueling Station

Project Value:

$1,488,000

Owner:

Compression Technology Corporation

Consultant:

Change Energy Services

Challenge:

  • Build a first-of-its-kind compressed natural gas fueling station located in Mississauga, Ontario.

Objective:

CSL acted as the Construction Management team in conjunction with Gain Fuel, The Emterra Group, Compression Technology Corporation, and CAT Trucks, to develop and build a natural gas fueling station.

Execution:

The project consisted of the demolition of existing site features, the installation of all the natural gas piping, storage tanks, compressors, generators, the creation of a new public fueling station, and the installation of trickle chargers for over 100 trucks.

[More]